Key takeaways
- Key to key time is measured from the day the keys come back to the day a new tenancy starts.
- Most lost days happen before or after the works: inspection, ordering, safety checks and sign off.
- A clear lettable standard and a contractor with spare capacity stop voids from piling up.
Empty homes are one of the most visible costs for a social landlord. While a property is void it earns no rent, it can attract damage, and a household that needs a home keeps waiting. Turnaround time is the number boards and regulators watch, and it is usually lost in small delays rather than in the building work itself.
Where the days go
| Stage | Common delay | What helps |
|---|---|---|
| Notice to keys | No inspection before the tenant leaves | Pre-termination visit to scope works early |
| Keys to start | Waiting for a survey or an order | Contractor surveys on the day the keys arrive |
| Safety checks | Gas, electrical and asbestos checks booked one after another | Book checks in parallel at the start |
| Works | Missing materials, wrong trades | Standard specification and stocked materials |
| Sign off | Waiting for an inspection slot | Photo evidence and a shared checklist |
Set a clear lettable standard
A written empty homes standard tells everyone what a finished void looks like: what gets replaced, what gets repaired, what gets cleaned and decorated. Without one, each property becomes a negotiation, and that costs days. Contractors should work to your standard, not their own.
Separate minor and major voids
Most empty homes need repairs, safety checks, cleaning and decoration. A smaller number need a full refurbishment, such as a new kitchen, bathroom or wet room. Routing the two types differently keeps the quick ones quick, instead of letting them queue behind the big jobs.
Plan for peaks with overspill capacity
Void numbers rise and fall. An overspill arrangement with a second contractor means the extra homes start straight away instead of waiting for the main team. UPS runs a voids overspill contract for West Lancashire Borough Council for exactly this reason: to help reduce turnaround times and the rent loss that comes with them.
Track it
- Measure each stage, not only the total, so you can see where days are lost.
- Use photos at handover so sign off does not wait for a site visit.
- Review repeat issues, such as the same item failing in several homes, and fix the cause.
How UPS helps
Our rapid response voids service covers everything from minor repairs to full house refurbishment, completed right first time to each client's empty homes standard. We currently deliver a 4 year voids contract for Magenta Living in Wirral.